Road Construction Project Updates

12197130_BG2

 

  • Clark Road – Hoping to pave early next week – will be doing some curb and gutter this week.
  • Millville Road – Hoping to pave early next week – doing drainage work and stone this week.
  • Lake Pleasant Road– May pave later this week depending on a meeting about guardrail tomorrow.
  • Imlay City Road– Scheduled to start next week
  • Millville/Oregon – Closed! Will be complete around the beginning of August.
  • Bowers Road – Tree Cutting should start Wednesday. It will be closed between Lk George and Lk Pleasant for thru traffic. Emergency vehicles can get through but will be delayed.
  • Elba Road – No more work this week except by AT&T.
  • John Conley Drive – Under construction, but open to traffic.